Resolution21-0260
Dept./ Agency: Engineering
Action: (X) Ratifying (X) Authorizing (X) Amending
Type of Service: Change Order/Amend Resolution 7R3-c adopted on February 3, 2021
Purpose: To provide an amendment to Contract 04-2014 (R), Broad Street at South Street, Tichenor Street and Lincoln Park Pedestrian Safety Project to increase the amount of the contract.
Entity Name: Berto Construction, Inc.
Entity Address: 625 Leesville Avenue, Rahway, New Jersey 07065
Contract Amount: Not to exceed $2,454,531.26
Funding Source: New Jersey Department of Transportation (NJDOT)
Contract Period: June 1, 2018 through October 25, 2020
Contract Basis: (X ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Original Resolution 7R3-a(s) adopted on May 9, 2017 awarded Contract 04-2014 (R) for a contract amount not to exceed $2,263,406.89 for the period of 365 consecutive calendar days from the issuance of a formal Notice to Proceed by the Director of the Department of Engineering.
Resolution 7R3-b(s) adopted on September 5, 2019 extended the substantial completion date to August 21, 2019, and a new final completion date of October 25, 2019.
Resolution 7R3-c adopted on February 3, 2021 extended the final completion date to October 25, 2020.
This Change Order/Amendment will increase the contract amount by $191,124.37 for a total contract amount not to exceed $2,454,531.26.
Introduced Feb 23, 2021· Engineering