All Legislation
Resolution2020-1028Passed

Resolution amending Resolution 37 of 2020 to allow for multiple agreements, as necessary, to authorize certain easements in connection with the construction of Duquesne Light Company’s new Riazzi Electric Substation (Substation) and the installation of an underground electrical system, to connect the Substation to the existing electrical distribution system for the surrounding area.

Progress

Introduced

Dec 23, 2020

In Committee

Dec 28, 2020

Passed

Jan 12, 2021

Enacted

Jan 12, 2021