All Legislation
Resolution2025-2580Passed

Resolution providing for an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Engineering, Final Design, and Right-of-Way phases of the West Carson Street Bridge project; providing for the payment of the costs thereof, not to exceed Two Million One Hundred Fifty Thousand Dollars ($2,150,000.00), an increase of One Million Two Hundred Fifty Thousand Dollars ($1,250,000.00) from the previously executed agreement. This resolution serves to authorize only the amended Reimbursement Agreement or Agreements, at a cost of Three Thousand Two Hundred Fifty Dollars ($3,250.00), an increase of One Thousand Seven Hundred Fifty Dollars ($1,750.00) from the previously executed agreement, to the City of Pittsburgh. Future Resolutions will authorize the project specific service agreements.

Progress

✓

Introduced

Nov 26, 2025

✓

In Committee

Dec 2, 2025

✓

Passed

Dec 16, 2025

✓

Enacted

Dec 16, 2025