All Legislation
Resolution2023-1169Passed

Resolution providing for an amended Reimbursement Agreement or Agreements with the Pittsburgh Water and Sewer Authority (PWSA) for costs associated with the West Ohio Street Bridge project where PWSA would be responsible for paying 100% of the actual expenses involved in certain work described herein and itemized in Exhibit “B” at an amount not to exceed Two Hundred and Eighty-Five Thousand Seven Hundred and Seventy-Seven Dollars and Twenty-Five Cents ($285,777.25) an increase of Fifty Four Thousand Three Hundred and Seventy Seven Dollars and Twenty Five Cents from the previously executed agreement (53176) as authorized by Resolution Number 636 of 2018.

Progress

Introduced

Jan 27, 2023

In Committee

Jan 31, 2023

Passed

Feb 14, 2023

Enacted

Feb 14, 2023