All Legislation
Resolution2024-0402Passed

Resolution amending Resolution 657 of 2022, which provided for an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design, Final Design, & Right of Way phases of the Swindell Bridge construction project, and providing for the payment of costs thereof, not to exceed Three Million Eight Hundred Thousand Dollars ($3,800,000.00), an increase of Two Million One Hundred Thousand Dollars ($2,100,000.00) from the previously executed agreement (54006.1); reimbursable at ninety five percent; and the municipal share of Commonwealth Incurred Costs not to exceed Seven Thousand Dollars ($7,000.00), Five Thousand Five Hundred Dollar ($5,500.00) increase from the previously executed agreement (54006.1).

Progress

Introduced

Apr 19, 2024

In Committee

Apr 22, 2024

Passed

May 7, 2024

Enacted

May 7, 2024